Bridge program of the LuFV II successfully completed

Since 2015, we have extensively renewed a total of 902 bridge constructions. As a result, the contractually prescribed target from the LuFV II of 875 was significantly exceeded. In addition to the modernization of the bridges, we are building and renovating road or pedestrian crossings, replacing the passageways and level crossings with new bridges and conducting ongoing renovation work on existing buildings. The sub-stance of the facilities is significantly improved by the high investment. Over the next ten years, the LuFV III will be used to tackle the renewal of a further 2,000 railway bridges.